In July 2026 MNRE extended a one-time exemption for net-metering and open-access solar projects. Projects commissioned by 31 December 2026 do not have to use solar cells from ALMM List-II, the approved list of cell manufacturers.
What this means in practice
- Commissioned by 31 December 2026: you can use non-DCR panels, which are made in India with imported cells and cost less.
- Commissioned after 31 December 2026: panels must use ALMM-listed cells, which cost more.
The deadline is about commissioning, not ordering. A business rooftop needs time for design, DISCOM feasibility, supply, installation and inspection, so plan backwards from the date.
A realistic timeline
- Site survey and engineering pack: about 1 week
- Order and DISCOM application: 1–2 weeks
- Supply and installation: about 15 days from order confirmation
- Inspection, net meter and commissioning: depends on your DISCOM